H1 insulation rules: what changes on 27 November 2026
- 5 October 2026
- Aaron Davis
The transition period for New Zealand's updated insulation rules ends on 26 November 2026. From 27 November, every building consent application for a new home must show compliance with the 6th edition of H1/AS1, not the 5th. If you're designing or pricing a build now, here's what that means.
The short version
MBIE says the overall level of insulation required hasn't changed. What has changed is how you prove it:
- No more schedule method. The table of minimum R-values that many designers relied on has been removed. Compliance is now shown with the calculation method or the modelling method.
- Framing is counted more honestly. Wall R-values must be worked out assuming at least 38% of the wall is framing, unless you can show a lower figure.
- Areas are measured from the inside, using overall internal dimensions for roofs, walls and floors.
- Slab-on-ground floors lose their separate minimum R-value in the calculation method, though the slab still counts in the overall heat loss.
- Better tables for windows and slabs cover more common situations.
Why the 38% framing rule matters
Timber is a poor insulator. Every stud, nog, plate and lintel is a path for heat to bypass the insulation beside it. Under the old approach many wall calculations assumed less framing than real walls have. Now a framing fraction of 38% is the default.
Here's a rough comparison for a 90mm timber-framed wall, looking at the insulation layer only. It's a simple area-weighted estimate for illustration, not a compliance calculation, and treats 90mm of timber as about R0.75.
| Wall build-up (90mm studs, 38% framing) | Approx. R-value of the insulation layer |
|---|---|
| R2.2 glass wool batts between studs | R1.3 |
| R2.8 glass wool batts between studs | R1.4 |
| R4.05 PIR (90mm) between studs | R1.5 |
| R2.8 batts between studs + 25mm PIR (R1.10) over the frame | R2.5 |
| R2.8 batts between studs + 40mm PIR (R1.80) over the frame | R3.2 |
Two things stand out. First, whatever you put between the studs, the framing drags the result down to around R1.3–R1.5. Second, a continuous layer over the frame isn't interrupted by timber, so its full R-value adds straight on. Just 25mm of PIR over the framing lifts the insulation layer by roughly 80%.
Your designer will do the full calculation to NZS 4214, including linings, air gaps and cladding, and the numbers will differ. But the pattern holds: under the new rules, the cheapest R-value in a wall is often a thin continuous layer outside the frame.
What this means for different projects
- Standard 90mm walls: batts alone may struggle in colder zones once 38% framing is applied. Options are 140mm framing, fewer studs where the engineering allows, or a continuous rigid layer.
- Renovations and reclads: a reclad is a good time to add PIR over the existing frame; see our drawing for exterior insulation to an existing wall.
- Tight spaces: where you can't make the wall thicker, a higher R-value per millimetre matters. Eurothane GP gives R4.05 in 90mm, against R2.8 for the best 90mm glass wool batt.
What to do before 27 November
- Check which edition your drawings use. A consent lodged on or after 27 November must use the 6th.
- Ask your designer to rerun the wall calculation with 38% framing.
- If walls come up short, price a continuous PIR layer against 140mm framing before redesigning.
Specifying for a project? Call us on 03 540 3003 or send us your plans and we'll help you choose thicknesses. See the price list; we supply anywhere in NZ with freight quoted on each order.
See also: NZ Building Code insulation requirements
This article is a general guide, not design advice. For the full requirements see MBIE's H1 page.
